Resource Leveling in MS Project
|
| Email Notifications OFF
|
| Original Post: Resource Leveling in MS Project |
|
1 posts |
Posted Aug 25, 2005 5:46 PM |
Auto leveling never seems to do what I expect it to do. So I end up having to switch it off and do the job myself. Has anyone else had the same experience or is it just me? I like MS Project and it is the only package that is support in my company so I don't really want to change. Is there anything I can do to allow me to do my really work?
Cheers |
|
| Replies |
Sort:
Newest First
Chronological
|
 | Anonymous |
|
Posted May 29, 2007 7:32 PM |
| Find Step By Step MS Project Tutorial
http://www.pmpbest.com/e107_plugins/links_page/links.php?cat.1
P.S:
----
1000's of PMP Exam Questions
Free Guide for PMP Exam
Loads of Reference Materials
Back Entry to Download Links
http://www.pmpbest.com/download |
|
3 posts |
Posted May 29, 2007 1:18 PM |
| Michael, along with the other good suggestions posted by the folks below, you may want to consider setting up a very simple project (build a fence) with just a single-resource and say 4 tasks: Fence Side A, Fence Side B, etc. Make note of a few different scenarios that you'd like to test for instance: a) what happens when I manually level 4 concurrently occuring, independent tasks that have the same resource? What would happen if I added a constraint to one of the tasks ie task must finish no later than...? What happens if I add non-working time to my resource's calendar ie vacation time, does the scheduler pick this up...? how does the scheduler determine which tasks should occur first when I have a series of tasks on the critical path and others that are not (try this with 4 tasks, 2 on a 'critical path' and 2 that are not?...etc, etc. If you start very simply, you can start to understand some of the basic functionality of the tool and also some of the idiosyncracies. Good luck! |
 | Anonymous |
|
Posted Mar 28, 2007 12:36 PM |
Hi Bethany -
I went to this url- http://office.microsoft.com/en-us/assistance/HA011587371033.aspx
and didn't know where to find the information. What user errors are you refering to? What specifically about this site helped you to do leveling? Was there one article or several tips\tricks?
I'm still looking for help on this topic.
Thank you
|
|
154 posts |
Posted Jan 4, 2006 10:25 AM |
A little late to post but thought I'd give it a shot anyways. A lot of people state that they have a problem with auto leveling in MS Project. However, in all the cases I have seen, it has been user error. There are many factors in setting up your project so that autolevel will work. From priortizing your deliverables (Project calls them tasks but strictly speaking from PM Literture, they should be deliverables), making sure you have accurately input your resources (accounting for productivity and availabilty - you may work an 8 hr day but we aren't actually working for 8 hours, you go to the bathroom, chat with your neighbors, etc..). A great resource for help with this is going to the MSProject - http://office.microsoft.com/en-us/assistance/HA011587371033.aspx
I have driven myself nuts with the autolevel til I found this site.
Good Luck! |
|
1 posts |
Posted Oct 26, 2005 6:10 PM |
MS Project has been by my side since 1983 (on&off). What made it simpler for me was to envision all of its tables as one large database. So to answer a question of "Is Bill (drafter) available for the times my projects will requirements? My project templates are already in boiler plate format with each task assigned two accounting codes. The first one is representative of the Work Package. the second the Work Element. First I would filter for only Drafting Tasks, this gives me the "Where." My team is informing me of the When, as I assign Bill onto his proper tasks, I load the Resource Graph on the top pane, and resource worksheet on the bottom pane. Since I'm using the project portfolio software, as I highlight my resource I also see how that resource is being utilized at any given time across the portfolio.
If management needed a cash flow forecast for the next 3 year for the entire portfolio. (The real question you need to see in your mind is: “when will the tasks happen and what does each one cost?” So, within a multi-project process, simply show the task usage table and in the right window [mouse - Right Click] select costs, and collapse all phases to the project level.
Hope I didn't confuse you even more . . |
|
4 posts |
Posted Oct 17, 2005 4:20 PM |
For years, I have struggled with MS Project. It seems to have a mind of it's own. But I just finished reading "Dynamic Scheduling with MS Office Project 2003" by Eric Uyttewaal, PMP and published by IIL. It's the only text book I've ever devoured as if it were a novel - every page brought new revelations. The first few chapters are a big "duh", but after that it becomes the most useful resource ever. Even if you have to purchase it yourself, it's worth it.
For the first time ever, I can update a schedule and not have to manipulate any fields. And I can confidently print a "slipping tasks" report without crossing my fingers.
And, by the way, only level resources if you have a resource-loaded plan. |
|
1 posts |
Posted Sep 26, 2005 2:56 PM |
I would be inclined to agree. I've never been able to satisfactorilly explain some of the goofy things Project does when trying to level resources.
This is in contrast to Primavera Project Planner, which never had this problem. The big difference is that Primavera is about 25k to implement, while anyone can pick up a copy of Project on Ebay for a couple of hundred bucks. The big problem is that Project is like a lot of other MS products (Access comes to mind immediately) in that it makes it easy to think you're accomplishing something when all you're doing is making pretty pictures. |
 | Anonymous |
|
Posted Sep 1, 2005 12:44 PM |
| We are going through a major implementation of MSProject in our organization, supported by the experts from Project Solutions Group. They say, never use autoleveling in MSProject -- you're asking for trouble! |
|
|
|
| Post to This Topic E-mail This Thread To A Friend |
sponsored announcements and special offers
CA Technologies' Innovation Management survey is a study into the barriers to innovation success and the measures companies are taking to improve performance. Each survey respondent will receive a complimentary copy of the report containing the survey's results. Please participate now!
Build and deploy interactive reports and dashboards — without any hidden costs. Our in-the-cloud free trial lets you see for yourself — no download required. SAP Crystal Reports Server 60-day Free Trial
Enable Agile Process; Support Agile Teams
CollabNet announces ScrumWorks Pro 4.4. As intuitive as Scrum itself, this version offers improvements in estimation and integration to CollabNet TeamForge. Improve your Scrum team's performance, enable tracking, view reports instantly, and effectively manage your Agile projects. Request a Trial
Enterprise hardware and software evolve faster than your customers can consume new versions and features. Overcome this gap: learn how professional services can boost product consumption and speed repurchasing in TSIA/Compuware white paper. Read now
Packaged Services Success: Join us on Sept 8 for this Free Webinar as RTM Consulting and Tenrox discuss the competitive and financial benefits of Leveraging Automation to meet the Rising Demand for Productized Professional Services. EARN 1 PDU. Register Here Today to receive a Free White Paper.
| "You can make more friends in two months by becoming interested in other people than you can in two years by trying to get other people interested in you." |
| - Dale Carnegie |
|
|